Toilet renovation is one of the most compact but technically complex types of renovation. Mistakes in planning can easily lead to delays, budget overruns, and conflicts with contractors. In this article, we will look at the actual timeframes for toilet renovation in Georgia, the stages of work, prices, and ways to get everything done faster and without unnecessary stress.
How long does toilet renovation take in practice?
On average, toilet renovation takes 5 to 20 days. The time frame depends on the condition of the room, the scope of work, and the availability of materials.
Average timeframes by type of renovation:
- cosmetic (without replacing pipes): 5—7 days;
- major: 10—14 days;
- renovation with relocation of plumbing fixtures: 15—20 days;
- turnkey renovation: 12—18 days.
Tbilisi and Batumi — the timeframes are similar, but during the high season (spring—summer), delays are possible due to the workload of the craftsmen.
The main stages of toilet renovation
Understanding the stages helps to control the timing and quality.
- Removal of old plumbing fixtures and tiles: 1—2 days.
- Replacement of pipes and electrical wiring: 2—3 days.
- Waterproofing: 1 day.
- Tile laying: 3—5 days.
- Installation of toilet and accessories: 1—2 days.
- Final inspection: 1 day.
If the bathroom is combined, add 2–4 days.
Toilet renovation prices in Georgia
Cost directly affects speed: cheap teams often drag out the process.
Average prices in Tbilisi and Batumi:
- cosmetic repairs: from 250—350 GEL/m²;
- major repairs: from 400—600 GEL/m²;
- turnkey repairs: from 550—750 GEL/m².
Prices do not include materials.
How to speed up toilet repairs without compromising on quality
- Purchase tiles and sanitary ware before starting work.
- Choose craftsmen with experience in bathrooms.
- Approve the plumbing and electrical plans in advance.
- Sign a contract with fixed deadlines.
- Do not change the design during the process.
Common mistakes that cause repairs to be delayed
- Lack of a project plan.
- Saving on waterproofing.
- Untested craftsmen hired through personal connections.
- Ordering materials as work progresses.
- Lack of control over the stages of work.
Mini‐case: how to get it done in 10 days
- Tbilisi, new building, toilet 2.1 m².
- The owner purchased tiles in advance, selected a contractor with a portfolio, and signed a contract.
- Result: major renovation — 9 working days, no additional payments or rework.
Facts about toilet repairs
- 70 % of delays are related to the delivery of materials.
- Waterproofing takes only 1 day, but saves years.
- The fastest repairs are in new buildings.
- Correcting mistakes increases the time frame by 30—40 %.
Frequently asked questions (FAQ)
1. How long does it take to renovate a small bathroom?
Usually 5—10 days with materials already on hand.
2. Is it possible to complete the renovation in a week?
Yes, if no pipes need to be moved and you have an experienced team.
3. What takes the longest?
Laying tiles and waiting for the layers to dry.
4. Is it possible to speed up the renovation without compromising on quality?
Yes, with good planning and the right contractor.
5. When is the best time to renovate in Georgia?
Fall and winter — there are fewer contractors available.
6. Do you need a design project for a bathroom?
It is desirable, even a simple one — it saves time and money.
Toilet renovation is not a “couple of days” job, but a clear process. If you want to stay on schedule and within budget in Tbilisi or Batumi, the key is preparation, experienced craftsmen, and stage control. This approach will save you from rework and unnecessary expenses.